Purpose

Prior to the commencement of construction, a Pre-Construction Meeting is held.The Pre-Construction Meeting is usually the first opportunity for the contractor and major subcontractors to meet with OSU departments

Responsibility & Timeline

The Project Manager (PM) should set up the pre-construction meeting after the construction contract has been executed.

Process

The following entities should be invited to the Pre-Construction Meeting:

  • Architect
  • Contractor
  • Major Subcontractors
  • OSU Facilities
  • OSU Capital Accounting
  • OSU Construction Contract Administration (CCA)
  • OSU Environmental Health & Safety (EH&S)
  • City of Corvallis
  • Building Manager
  • Parking Services
  • Equal Opportunity and Access (EOA)

Use the attached Pre-Construction Sign-In Sheet to document attendance.

Use the attached Pre-Construction Meeting Agenda to facilitate the meeting.

Take Meeting Notes and distribute to attendees.